July 14, 2016

Expand
Close
Expand
Close

Here's our monthly construction progress update, courtesy of Jeremy Wright, our construction project manager for one of the largest projects we've ever undertaken as a Design-Builder the Seaboard - Triumph Foods Pork Processing Plant in Sioux City, Iowa.

What you see here are few aerials of the 245-acre site showing our construction progress which Jeremy describes thusly,

'The equipment vendor, MPS, has completed the Pre-Shell installation of the Stun Pits' as well as setting of the Dehairer. Our plumber has begun laying pipe in Kill Floor. Our steel erector has moved into Welfare to begin erecting steel today. Rendering foundations are complete and steel erection in Rendering began last week. Preston now has 13 units hung in EQ. The insulated metal panel work has started to progress and we continue to place footings in the distribution area.'

The 750,000 square foot Seaboard Farms Triumph Foods facility is budgeted at $264M and is scheduled to be completed mid-2017.